Production Rate Tracking

Record actual hours per task after every job. After 5-10 entries, the average becomes your production rate.

After every job, record actual hours and crew size for each task. After five entries, you have a usable average. After ten, a reliable production rate. That rate goes directly into your estimating system. Over the first year, you build rates for your twenty to thirty most common tasks.